275kV Chita Thermal Line Refurbishment Project

The 275kV Chita Thermal Line was constructed over 50 years ago. Concerns have arisen about deterioration of both the pylons and power lines. There are also many areas where power line ground clearance is low, potentially impeding development of the surrounding land, so Chubu Electric Power Grid is moving forward with a refurbishment project to reconstruct pylons and rewire power lines.

Project Overview

Foundation Work

Pile construction under the transmission line
Pile construction under the transmission line

Stringing Construction

Transmission line extending
Transmission line extending
Tensing work on the transmission line
Tensing work on the transmission line

Steel Tower Assembly

Steel tower assembly by climbing crane
Steel tower assembly by climbing crane
Rebuilding by wrapping the existing steel tower
Rebuilding by wrapping the existing steel tower

Construction of New Hida Converter Station and Expansion of Higashi-Shimizu Substation Frequency Converter (FC)

If a large-scale power shutdown occurs as happened after the 2011 Great East Japan Earthquake, events may arise that have a significant social impact, such as the implementation of planned power outages. In order to address such events before they happen, Chubu Electric Power Grid is proceeding with a project to construct the new Hida Converter Station (900,000 kW) by March 2021 and expand the Higashi-Shimizu Substation Frequency Converter (600,000 kW) by March 2028 as part of our efforts to augment capacity for mutual support between 50 and 60 Hz areas.

Overview of Hida Converter Station

Schematic Diagram

Schematic Diagram

Single-line Diagram

Single-line Diagram

Work Schedule

Work Schedule

Status

Overview
Overview
Thyristor valve
Thyristor valve
Harmonic filter
Harmonic filter

Schematic Diagram

Schematic diagram

Overview

Overview

275 kV Higashi-Nagoya-Toubu Line Refurbishment Project

The 275 kV Higashi-Nagoya-Toubu Line was constructed in 1967 and the time has come for the equipment to be renovated. Chubu Electric Power Grid has been moving forward with this project in steps, beginning with sectors that are highly urbanized. Phase 1 was a line sector of approximately 11 km in length in Aichi Prefecture’s Miyoshi and Toyota cities. The rebuilding of 24 pylons and rewiring of power lines to standard gauge wire was completed in May 2018. This has been followed by Phase 2, a sector of line approximately 15 km in length traversing Obu, Toyoake, Kariya, Miyoshi and Toyota cities. The work of rebuilding 40 pylons and rewiring power lines, including adjusting spans around the Higashi-Nagoya Substation, will take until June 2025.

275 kV Higashi-Nagoya-Toubu Line Refurbishment Project

Status of Phases 1 and 2

Status of Phases 1 and 2

Go to the Top of the Page